👍 dzisiaj nie specjalnie robie to co powinienem ale no cóż nie mam serca do tego
|
||||
|
||||
|
||||
Project migration
|
||||
### Notatki ze spotkania
|
||||
|
||||
Naser confirmed they have the Excel document needed for the migration steps.
|
||||
Paweł mentioned the body will make the decision regarding the migration.
|
||||
Project leadership
|
||||
**1. Migracja projektu**
|
||||
- **Naser** potwierdził, że posiadają dokument Excel niezbędny do wykonania kroków migracyjnych.
|
||||
- **Paweł** wspomniał, że decyzję dotyczącą migracji podejmie odpowiedni organ decyzyjny.
|
||||
|
||||
Naser confirmed they will lead the project and had a handover meeting with Kamil two weeks ago.
|
||||
Migration decisions
|
||||
**2. Kierownictwo projektu**
|
||||
- **Naser** potwierdził, że poprowadzi projekt. Dwa tygodnie temu odbyło się spotkanie przekazujące (handover) z Kamilem.
|
||||
|
||||
The team decided that the three database clusters will remain in CGI due to potential latency concerns with OVH.
|
||||
The team agreed to keep the database clusters in CGI due to latency concerns with OVH
|
||||
Project tracking
|
||||
**3. Decyzje i planowanie migracji**
|
||||
- Zespół zdecydował, że trzy klastry baz danych pozostaną w CGI ze względu na potencjalne obawy dotyczące opóźnień (latency) w przypadku OVH.
|
||||
- Omówiono wymagania dotyczące wersji SQL Server: **Paweł** potwierdził konieczność zastosowania jednoetapowej ścieżki aktualizacji z wersji 8 (2008) do 14 (2014), a następnie do 22 (2022).
|
||||
- **Jimmy** zasugerował zamontowanie nowego dysku na kopie zapasowe w VMware i zlecenie zespołowi CGI przełączenia go na drugi serwer jako standardowego dysku lokalnego, aby przyspieszyć proces migracji.
|
||||
- Zespół omówił wady i zalety korzystania ze współdzielonego dysku kopii zapasowych między starymi a nowymi serwerami, ostatecznie decydując, że może to nie mieć sensu ze względu na różnice między klastrami.
|
||||
- Przeanalizowano również specyfikację nowego serwera (wymagania dotyczące procesora, pamięci RAM, przestrzeni swap oraz dysku na kopie zapasowe).
|
||||
|
||||
Naser emphasized the importance of creating and updating individual tickets for each migration task to demonstrate ongoing work.
|
||||
Migration planning
|
||||
|
||||
Participants discussed the SQL Server version requirements for migration, confirming the need for a one-step upgrade path from version 8 to 14 and then to 22.
|
||||
Jimmy suggested mounting a new backup drive in VMware and having CGI flip it over to the second server as a standard local drive to speed up the migration process.
|
||||
Participants discussed the pros and cons of using a shared backup drive between old and new servers, ultimately deciding that it may not make sense due to cluster differences.
|
||||
Paweł confirmed the need for a one-step upgrade path from SQL version 8 to 14 and then to 22 for the migration.
|
||||
Participants discussed the specifications for the new server, including CPU, RAM, swap, and backup drive requirements.
|
||||
Migration progress
|
||||
|
||||
Paweł confirmed that the databases within the box loop have been migrated to the new server and are disabled in the cluster.
|
||||
Jimmy confirmed that Frederick Rodin has already requested new servers and moved the Bart databases.
|
||||
Participants agreed to wait until the blue cluster migration is complete before proceeding with additional server orders to avoid unnecessary costs.
|
||||
Uppföljningsuppgifter
|
||||
|
||||
Uppgift Tilldelats till Förfallodatum Hink
|
||||
Restart migration process for the three database clusters in SE (Naser, Paweł)
|
||||
Confirm when the Windows team will prepare the systems for migration (Naser)
|
||||
Set the project due date to October 30th for the migration of the database clusters (Naser, Paweł)
|
||||
Request new servers for the database clusters with specifications copied one-to-one from the old servers (Windows team)
|
||||
Create individual tickets for each migration task and update them as progress is made (Naser)
|
||||
Prepare the list of required database backup disks for migration and send to Naser after the meeting (Paweł)
|
||||
Send the SQL disk configuration details, including number and usage of disks, to Jimmy (Paweł)
|
||||
Prepare the list of required database backup disks for migration and send to Naser after the meeting (Paweł)
|
||||
Send the SQL disk configuration details, including number and usage of disks, to Jimmy (Paweł)
|
||||
Provide the list of required disks for migration to Naser (Paweł)
|
||||
Order new servers for the migration with the listed disks (Naser)
|
||||
Decide backup drive size for the new server, opting for 500 gigabytes for temporary backups (Jimmy, Grzegorz, Paweł, Naser)
|
||||
Submit the server request and push it to Leszek to expedite the CGI process (Naser)
|
||||
**4. Postępy migracji i śledzenie projektu**
|
||||
- **Naser** podkreślił znaczenie tworzenia i regularnego aktualizowania indywidualnych zgłoszeń (ticketów) dla każdego zadania migracyjnego, aby zapewnić widoczność postępów prac.
|
||||
- **Paweł** potwierdził, że bazy danych "box loop" zostały zmigrowane na nowy serwer i pomyślnie wyłączone w klastrze.
|
||||
- **Jimmy** potwierdził, że Frederick Rodin zgłosił zapotrzebowanie na nowe serwery i przeniósł bazy danych "Bart".
|
||||
- Zespół zgodził się wstrzymać z zamawianiem dodatkowych serwerów do czasu zakończenia migracji "niebieskiego klastra" (blue cluster), aby uniknąć niepotrzebnych kosztów.
|
||||
|
||||
### Zadania do wykonania (Follow-up tasks)
|
||||
|
||||
| Zadanie | Przypisane do | Termin |
|
||||
| :--------------------------------------------------------------------------------------------------------------------------------------------- | :---------------------------- | :----- |
|
||||
| Wznowienie procesu migracji dla trzech klastrów baz danych w Szwecji (SE) | Naser, Paweł | |
|
||||
| Potwierdzenie terminu przygotowania systemów do migracji przez zespół Windows | Naser | |
|
||||
| Ustalenie deadline'u migracji klastrów baz danych na 30 października | Naser, Paweł | |
|
||||
| Zamówienie nowych serwerów (specyfikacja sprzętowa skopiowana 1:1 ze starych maszyn i zaktualizowana o dodatkowe dyski na backup) | Zespół Windows, Naser | |
|
||||
| Decyzja o rozmiarze dysku na kopie zapasowe dla nowego serwera (wybrano 500 GB na tymczasowe backupy) | Jimmy, Grzegorz, Paweł, Naser | |
|
||||
| Utworzenie ticketów dla każdego zadania migracyjnego i ich systematyczna aktualizacja | Naser | |
|
||||
| Przygotowanie po spotkaniu pełnej listy oraz specyfikacji wymaganych dysków (w tym użycie i ich ilość) i wysłanie jej do Nasera oraz Jimmy'ego | Paweł | |
|
||||
| Przekazanie wniosku o serwery do Leszka w celu przyspieszenia procesu po stronie CGI | Naser | |
|
||||
|
||||